Building Near the Shoreline at Smith Mountain Lake: AEP Rules & the 800-Foot Contour

Everything below the 800-foot contour at Smith Mountain Lake is managed by Appalachian Power under its federal hydroelectric license. Here is what that means for patios, pergolas, pavilions, docks, and tree removal on lakefront property — and how to plan a project that clears both AEP and the county. Reviewed August 2026.

NOW SERVING SMITH MOUNTAIN LAKE & FRANKLIN COUNTY

Two Rulebooks Govern Every Lakefront Project

Smith Mountain Lake operates at a full-pond elevation of 795 feet above sea level. The project boundary — the line where Appalachian Power's authority begins — sits at the 800-foot contour (NGVD 29). Below that line, AEP's Shoreline Management Plan controls what can be built, planted, cleared, or excavated, under license from the Federal Energy Regulatory Commission. Above the contour, normal county rules apply: Franklin County or Bedford County building permits, zoning setbacks, and Virginia's statewide building code. Most patios, pergolas, and pavilions are built above the 800-foot line and are county matters — the shoreline work that connects them to the water, such as steps, stabilization, vegetation clearing, and docks, is where AEP permits come in.

Stamped concrete pool deck with spa spillover and grill island overlooking Smith Mountain Lake near Union Hall VA
DESIGNED WITH THE PROPERTY

Above the 800-Foot Contour: County Territory

Outdoor living structures on lakefront lots follow the same permitting as anywhere in Franklin or Bedford County — with extra attention to slope, setbacks, and erosion control. On steep grades the retaining wall, not the patio, is often the permitted element, and septic field locations frequently dictate where a structure can legally sit on lake parcels.

Motorized louvered pergola over a poolside fire table lounge overlooking Smith Mountain Lake near Moneta VA
A CATEGORY-DEFINING APPLICATION

Below the Contour: AEP Occupancy & Use Permits

Docks, boat lifts, riprap, excavation, and shoreline stabilization below the 800-foot line require an Occupancy and Use Permit from Appalachian Power — regardless of what the deed says about the land. As of July 31, 2026, new Occupancy and Use Permits are valid for two years from issuance instead of one, which gives larger projects room to sequence shoreline and upland phases together.

OUR APPROACH

Vegetation and View Corridors Are Permitted, Too

Removing any vegetation of half an inch in diameter or larger within the project boundary requires an AEP Vegetation Removal Permit — and that includes clearing for lake views. Plan the view corridor as part of the landscape design: approved selective thinning and pruning achieve more than an application to clear-cut ever will.

Timber-frame pool pavilion with outdoor kitchen and fireplace at dusk on Smith Mountain Lake VA
DESIGNED FOR LAKE LIVING

Design Once, Permit Both

The projects that stall at Smith Mountain Lake are the ones designed before anyone verified the contour line. Allscape sequences it in one pass: survey the 800-foot boundary, place structures and hardscape in county jurisdiction, and scope the AEP-permitted shoreline work alongside — so the patio, the path to the water, and the dock arrive as one coordinated, approvable plan.

WHAT WE BUILD

Who Permits What at Smith Mountain Lake

The fastest way to understand a lakefront project: split it at the 800-foot contour and assign each piece to its authority.

County Side — Above 800 Feet

Patios, decks, pergolas, pavilions, and pools. Franklin or Bedford County permits, zoning setbacks, and the Virginia USBC. See our Franklin County permit guide for thresholds.

AEP Side — Below 800 Feet

Docks, boat lifts, riprap, excavation, stabilization, and steps to the water. Occupancy & Use Permit from Appalachian Power — two-year validity as of July 2026.

Vegetation — Within the Boundary

Any removal of vegetation half an inch in diameter or larger requires an AEP Vegetation Removal Permit — including clearing for views. Selective, approved pruning beats denial letters.

FAQ

Smith Mountain Lake Shoreline Questions, Answered

Direct answers on how Appalachian Power's Shoreline Management Plan interacts with county permitting for outdoor living projects at Smith Mountain Lake.

Can I build a patio or pergola near the water at Smith Mountain Lake?

Yes — if it sits above the 800-foot contour, it is a county permitting matter in Franklin or Bedford County. Below the contour, construction requires Appalachian Power approval, which is generally reserved for water-dependent structures like docks and shoreline stabilization.

Who controls the land below the 800-foot contour?

Appalachian Power manages it under its FERC hydroelectric license and Shoreline Management Plan. Even where a deed extends toward the water, AEP approval governs construction, excavation, and vegetation removal below the line.

Do I need permission to clear trees for a lake view?

Yes, within the project boundary. Any vegetation half an inch in diameter or larger requires an AEP Vegetation Removal Permit. AEP favors selective thinning and pruning over clearing — design the view corridor accordingly.

How long is an AEP dock or shoreline permit valid?

Occupancy and Use Permits issued on or after July 31, 2026 are valid for two years from issuance — recently doubled from one year — which makes it practical to phase shoreline work with a larger outdoor living project.

What is the normal water level at Smith Mountain Lake?

Full pond is 795 feet above sea level; the project boundary is the 800-foot contour (NGVD 29). The five-foot band between them is where lakefront surprises happen — verify the contour with a survey before designing anything near the water.

Does a lakefront pool have special requirements?

The pool itself is county-permitted like any other, with Virginia's 48-inch barrier code applying. What changes on lake lots: setbacks, slope engineering, and drainage planning — and any related shoreline stabilization falls under AEP.

Which county permits my Smith Mountain Lake property?

The lake spans Franklin, Bedford, and Pittsylvania counties. Westlake and the Rocky Mount side are Franklin County; Moneta and Huddleston are largely Bedford County. Your tax parcel — not your mailing address — decides the office.
SERVICE AREA

Communities This Guide Covers

Smith Mountain Lake shoreline parcels in Moneta, Westlake, Hardy, Huddleston, Wirtz, Penhook, Union Hall, Goodview, and Glade Hill — spanning Franklin and Bedford counties. AEP's Shoreline Management Plan applies lake-wide; which county rules apply depends on the parcel.

START THE CONVERSATION

Planning a Lakefront Outdoor Living Project?

Allscape designs to the contour line: structures and hardscape in county jurisdiction, shoreline work scoped for AEP, one coordinated approval path. Share the property and we will map what is possible.